Ronald O'Rourke
Specialist in Naval Affairs
CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN- 78) class of nuclear-powered aircraft carriers (CVNs).
CVN-78 was procured in FY2008 and is being funded with congressionally authorized four-year incremental funding in FY2008-FY2011. The Navy’s proposed FY2012 budget estimates the ship’s procurement cost at $11,531.0 million (i.e., about $11.5 billion) in then-year dollars. The Navy’s proposed FY2011 budget requested $1,731.3 million in procurement funding as the final increment to complete this estimated procurement cost.
CVN-79 is scheduled for procurement in FY2013, and has received advance procurement funding since FY2007. The Navy’s proposed FY2012 budget estimates the ship’s procurement cost at $10,253.0 million (i.e., about $10.3 billion) in then-year dollars and requests $554.8 million in advance procurement funding for the ship.
CVN-80 is scheduled for procurement in FY2018, with advance procurement funding scheduled to begin in FY2014. The Navy’s proposed FY2012 budget estimates the ship’s procurement cost at $13,494.9 million (i.e., about $13.5 billion) in then-year dollars.
On April 6, 2009, Secretary of Defense Robert Gates announced a number of recommendations he was making to the President for the FY2010 defense budget submission. One of these was to shift procurement of carriers to five-year intervals. This recommendation, which was included in the FY2010 defense budget submission, deferred the scheduled procurement of CVN-79 from FY2012 to FY2013, and the scheduled procurement of CVN-80 from FY2016 to FY2018. Secretary of Defense Robert Gates stated on April 6, 2009, that shifting carrier procurement to five-year intervals would put carrier procurement on “a more fiscally sustainable path.”
Oversight issues for Congress for the CVN-78 program include technical risk and the potential for cost growth on CVNs 78, 79, and 80, and technical and design issues for CVN-78 class carriers that were raised in a December 2010 report from the Department of Defense (DOD) Director of Operational Test and Evaluation (DOT&E).
Date of Report: April 12, 2011
Number of Pages: 25
Order Number: RS20643
Price: $29.95
Follow us on TWITTER at http://www.twitter.com/alertsPHP or #CRSreports
Document available via e-mail as a pdf file or in paper form.
To order, e-mail Penny Hill Press or call us at 301-253-0881. Provide a Visa, MasterCard, American Express, or Discover card number, expiration date, and name on the card. Indicate whether you want e-mail or postal delivery. Phone orders are preferred and receive priority processing.
Specialist in Naval Affairs
CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN- 78) class of nuclear-powered aircraft carriers (CVNs).
CVN-78 was procured in FY2008 and is being funded with congressionally authorized four-year incremental funding in FY2008-FY2011. The Navy’s proposed FY2012 budget estimates the ship’s procurement cost at $11,531.0 million (i.e., about $11.5 billion) in then-year dollars. The Navy’s proposed FY2011 budget requested $1,731.3 million in procurement funding as the final increment to complete this estimated procurement cost.
CVN-79 is scheduled for procurement in FY2013, and has received advance procurement funding since FY2007. The Navy’s proposed FY2012 budget estimates the ship’s procurement cost at $10,253.0 million (i.e., about $10.3 billion) in then-year dollars and requests $554.8 million in advance procurement funding for the ship.
CVN-80 is scheduled for procurement in FY2018, with advance procurement funding scheduled to begin in FY2014. The Navy’s proposed FY2012 budget estimates the ship’s procurement cost at $13,494.9 million (i.e., about $13.5 billion) in then-year dollars.
On April 6, 2009, Secretary of Defense Robert Gates announced a number of recommendations he was making to the President for the FY2010 defense budget submission. One of these was to shift procurement of carriers to five-year intervals. This recommendation, which was included in the FY2010 defense budget submission, deferred the scheduled procurement of CVN-79 from FY2012 to FY2013, and the scheduled procurement of CVN-80 from FY2016 to FY2018. Secretary of Defense Robert Gates stated on April 6, 2009, that shifting carrier procurement to five-year intervals would put carrier procurement on “a more fiscally sustainable path.”
Oversight issues for Congress for the CVN-78 program include technical risk and the potential for cost growth on CVNs 78, 79, and 80, and technical and design issues for CVN-78 class carriers that were raised in a December 2010 report from the Department of Defense (DOD) Director of Operational Test and Evaluation (DOT&E).
Date of Report: April 12, 2011
Number of Pages: 25
Order Number: RS20643
Price: $29.95
Follow us on TWITTER at http://www.twitter.com/alertsPHP or #CRSreports
Document available via e-mail as a pdf file or in paper form.
To order, e-mail Penny Hill Press or call us at 301-253-0881. Provide a Visa, MasterCard, American Express, or Discover card number, expiration date, and name on the card. Indicate whether you want e-mail or postal delivery. Phone orders are preferred and receive priority processing.