The Navy’s proposed FY2013 budget requests $3,217.6 million in procurement funding to complete the procurement cost of the 17th and 18th Virginia (SSN-774) class nuclear-powered attack submarines. The FY2013 budget estimates the combined procurement cost of these two boats at $5,107.9 million, and the ships have received a total of $1,890.3 million in prior-year advance procurement (AP) and Economic Order Quantity (EOQ) funding. The Navy’s proposed FY2013 budget also requests $874.9 million in AP funding for Virginia-class boats to be procured in future years. The Navy’s proposed FY2013 budget defers the scheduled procurement of one Virginia-class boat from FY2014 to FY2018.
The two Virginia-class boats requested for procurement in FY2013 are the final two in a group of eight covered by a multiyear procurement (MYP) arrangement for the period FY2009-FY2013. The Navy this year is requesting congressional approval for a new MYP arrangement that would cover the next nine Virginia-class boats scheduled for procurement in FY2014-FY2018 (in annual quantities of 1-2-2-2-2).
The Department of Defense (DOD) announced in January 2012 that it wants to build Virginiaclass boats procured in FY2019 and subsequent years with an additional mid-body section, called the Virginia Payload Module (VPM), that contains four large-diameter, vertical launch tubes that the boats would use to store and fire additional Tomahawk cruise missiles or other payloads, such as large-diameter unmanned underwater vehicles (UUVs). Building Virginia-class boats with the VPM might increase their unit procurement costs by about 15%-20%, and would increase the total number of torpedo-sized weapons (such as Tomahawks) that they could carry by about 76%.
The Navy’s FY2013 30-year SSN procurement plan, if implemented, would not be sufficient to maintain a force of 48 SSNs consistently over the long run. The Navy projects under that plan that the SSN force would fall below 48 boats starting in FY2022, reach a minimum of 43 boats in FY2028-FY2030, and remain below 48 boats through FY2034.
Potential issues for Congress regarding the Virginia-class program include the following:
Specialist in Naval Affairs
The Navy’s proposed FY2013 budget requests $3,217.6 million in procurement funding to complete the procurement cost of the 17th and 18th Virginia (SSN-774) class nuclear-powered attack submarines. The FY2013 budget estimates the combined procurement cost of these two boats at $5,107.9 million, and the ships have received a total of $1,890.3 million in prior-year advance procurement (AP) and Economic Order Quantity (EOQ) funding. The Navy’s proposed FY2013 budget also requests $874.9 million in AP funding for Virginia-class boats to be procured in future years. The Navy’s proposed FY2013 budget defers the scheduled procurement of one Virginia-class boat from FY2014 to FY2018.
The two Virginia-class boats requested for procurement in FY2013 are the final two in a group of eight covered by a multiyear procurement (MYP) arrangement for the period FY2009-FY2013. The Navy this year is requesting congressional approval for a new MYP arrangement that would cover the next nine Virginia-class boats scheduled for procurement in FY2014-FY2018 (in annual quantities of 1-2-2-2-2).
The Department of Defense (DOD) announced in January 2012 that it wants to build Virginiaclass boats procured in FY2019 and subsequent years with an additional mid-body section, called the Virginia Payload Module (VPM), that contains four large-diameter, vertical launch tubes that the boats would use to store and fire additional Tomahawk cruise missiles or other payloads, such as large-diameter unmanned underwater vehicles (UUVs). Building Virginia-class boats with the VPM might increase their unit procurement costs by about 15%-20%, and would increase the total number of torpedo-sized weapons (such as Tomahawks) that they could carry by about 76%.
The Navy’s FY2013 30-year SSN procurement plan, if implemented, would not be sufficient to maintain a force of 48 SSNs consistently over the long run. The Navy projects under that plan that the SSN force would fall below 48 boats starting in FY2022, reach a minimum of 43 boats in FY2028-FY2030, and remain below 48 boats through FY2034.
Potential issues for Congress regarding the Virginia-class program include the following:
- whether to approve the Navy’s request for a new MYP arrangement for the nine Virginia-class boats scheduled for procurement in FY2014-FY2018;
- whether to restore procurement of a second Virginia-class boat in FY2014—an issue that could have implications for Virginia-class AP funding in FY2013;
- the Virginia-class procurement rate more generally in coming years, particularly in the context of the projected SSN shortfall and the larger debate over future U.S. defense strategy and defense spending; and
- Virginia-class program issues raised in a December 2011 report from DOD’s Director, Operational Test and Evaluation (DOT&E).
The Navy’s Ohio Replacement (SSBN[X]) ballistic missile submarine program is
discussed in CRS Report R41129, Navy Ohio Replacement (SSBN[X])
Ballistic Missile Submarine Program: Background and Issues for Congress,
by Ronald O'Rourke. .
Date of Report: December 21, 2012
Number of Pages: 33
Order Number: RL32418
Price: $29.95
To Order:
Date of Report: December 21, 2012
Number of Pages: 33
Order Number: RL32418
Price: $29.95
To Order:
RL32418.pdf to use the SECURE SHOPPING CART
e-mail congress@pennyhill.com
Phone 301-253-0881
For email and phone orders, provide a Visa, MasterCard, American Express, or Discover card number, expiration date, and name on the card. Indicate whether you want e-mail or postal delivery. Phone orders are preferred and receive priority processing.