Moshe
Schwartz
Specialist in Defense Acquisition
On
September 8, 1982, President Ronald Reagan signed into law the Department of
Defense (DOD) Authorization Act, 1983 (P.L. 97-252), which included what
has come to be known as the Nunn-McCurdy Act (10 U.S.C. §2433). The
Nunn-McCurdy Act requires DOD to report to Congress whenever a major
defense acquisition program experiences cost overruns that exceed certain
thresholds. The purpose of the act was to help control cost growth in major
defense systems by holding the appropriate Pentagon officials and defense
contractors publicly accountable and responsible for managing costs.
A program that experiences cost growth exceeding any of the established
thresholds is said to have a Nunn-McCurdy breach. There are two types of
breaches: significant breaches and critical breaches. A “significant”
breach is when the Program Acquisition Unit Cost (the total cost of development,
procurement, and construction divided by the number of units procured) or the Procurement
Unit Cost (the total procurement cost divided by the number of units to be
procured) increases 15% or more over the current baseline estimate or 30%
or more over the original baseline estimate. A “critical” breach occurs
when the program acquisition or the procurement unit cost increases 25% or
more over the current baseline estimate or 50% or more over the original
baseline estimate.
The Nunn-McCurdy Act has been statutorily amended a number of times over the
years. One of the most significant changes to the reporting requirements
occurred in the FY2006 National Defense Authorization Act (P.L. 109-163),
when Congress added the original baseline estimate as a threshold against
which to measure cost growth. The new standard prevents DOD from avoiding
a Nunn-McCurdy breach by simply re-baselining a program. Another significant
change occurred in the FY2009 Weapon Systems Acquisition Reform Act (P.L.
111-23), when Congress enacted a requirement that programs with critical
breaches should be presumed terminated unless the Secretary of Defense
certifies the program. For programs that are certified, DOD generally must
(1) revoke the prior milestone approval, (2) restructure the program, and (3)
provide Congress a written explanation of the root cause of the cost
growth. These changes were fueled in part over congressional concern that
programs with chronic cost growth and schedule delays were not being
terminated and Congress was not being provided specific information explaining
what caused the cost growth.
Some analysts believe that the Nunn-McCurdy Act has been effective as a
reporting mechanism for informing Congress of cost overruns in major
acquisition programs. As a result of the Nunn- McCurdy process, Congress
has increased its visibility into the cost performance of the acquisition
stage of Major Defense Acquisition Programs (MDAPs). However, some analysts suggest
that Nunn-McCurdy is not a sufficiently comprehensive reporting mechanism
because program managers can sometimes take steps to avoid a breach and
because Nunn-McCurdy does not apply to all elements of a weapon system’s
life-cycle costs, such as its operations, support, or disposal costs.
Date of Report: December 26, 2012
Number of Pages: 33
Order Number: R41293
Price: $29.95
To Order:
R41293.pdf
to use the SECURE SHOPPING CART
e-mail congress@pennyhill.com
Phone
301-253-0881
For email and phone orders, provide a Visa, MasterCard, American Express, or Discover card
number, expiration date, and name on the card. Indicate whether you want e-mail
or postal delivery. Phone orders are preferred and receive priority processing.